Australia’s National Electricity Market (NEM) has one of the world’s largest battery energy storage pipelines. Over 17 GW of projects are attempting to start operation by the end of 2027. However, the success on this pipeline getting built depends on each project’s ability to achieve financing and then its ability to be built and commissioned.
This article provides an update on the progress of battery energy storage projects in the NEM: what projects came online in the first quarter of 2025, how the remainder of the pipeline is progressing, and what this means for our expectations of battery buildout through to the end of 2027.
This article builds upon our 2025 NEM Pipeline Report. You can read it here.
In the first three months of 2025, 155 MW (310 MWh) of new battery energy storage began commercial operations in the NEM. This was eclipsed by a further 200 MW / 400 MWh in April. This brings commercially operational battery capacity in the NEM to 2.4 GW and 3.8 GWh (as of 1st May).
Skip the extension — just come straight here.
We’ve built a fast, permanent tool you can bookmark and use anytime.
Go To Paywall Unblock Tool